Information about the project

Project status

Completed project

Category

Energy and industrial engineering

Title object

Condenser ТГ-2 on power unit №2 SUNPP

Shape attend

General contractor

Customer

South-Ukraine NPP "NNEGC "Energoatom"

Terms of works

August 2015 - December 2015

Replacement of condenser ТГ-2 on power unit №2 South-Ukraine NPP

The project provides execution of works for replacement of condenser ТГ-2 on power unit №2 South-Ukraine NPP. There will be dismantling of old condenser type К-45600 and installation of new condenser type К-57530 (produced in Ukraine) set Б, which includes three bodies. Replacement of the equipment shall allow turbine unit to operate at rated capacitance at changes of temperature of cooling water as well as provide capacity gain and operation of the power unit within prolonged lifespan.